MTU Kerry
Disciplines coordinated
The brief
MTU Kerry's new STEM building required a digital construction management workflow connecting design, procurement and on-site progress. Bimco set up a federated Revit environment, weekly Navisworks coordination and a cost-loaded Synchro 4D model.
How we delivered it
Site progress was captured fortnightly using 360° camera walks and overlaid against the planned model in BIM Track. A live Power BI dashboard surfaced earned-value, programme drift and outstanding RFIs to the client team.
The outcome
The project was delivered three weeks ahead of programme and 1.8% under budget — a result the client attributes directly to the upfront digital coordination effort.
Working on education projects
Education estates are typically phased around term dates and occupied throughout, so the constraint is rarely the modelling — it is scheduling capture and works around a building that cannot close.